Building St Mary's Wharf on Millbrook will need two tower cranes and up to 13 lorries a day at its peak in late 2027. The contractor's plan runs to the end of 2028.

Building the 180 homes at St Mary’s Wharf, on the former Debenhams site in Millbrook, will take until the end of 2028. The busiest period for lorries will come in late 2027, with up to 13 construction vehicles a day.

The figures come from a construction logistics plan by Bennett Construction, the main contractor. The developer’s agent sent it to Guildford Borough Council on 16 November for approval under condition 50 of the 2022 planning permission (planning register, 23/D/00169/15). Work cannot go ahead on the main build until the council approves a plan of this kind. Two linked applications, for the construction environment plan and the site waste plan, were validated in the same week.

What it means for Millbrook

The plan says the site will be run from its Millbrook (A281) frontage. It sets out:

  • site hoarding extending over the Millbrook pavement along the site frontage, subject to highway approval
  • pedestrians sent to the opposite pavement, using the existing crossings at each end
  • a “pit lane” on Millbrook where lorries pull in to unload, with gates manned by traffic marshals
  • two tower cranes, two goods hoists and a telehandler on site
  • temporary lane or road closures for big lifts, including putting up and taking down the tower cranes

The plan says Surrey Highways has approved the pit lane layout. Bennett will run it full time from January 2027. Any road closure would need its own approval and traffic order.

When lorries will come

Every delivery must be booked in advance. Unbooked vehicles will be turned away, and none may wait or queue on Millbrook. Deliveries are limited to site working hours:

Day Delivery hours
Monday to Friday 8am to 6pm
Saturday 8am to 1pm

The plan adds that no deliveries should arrive during school drop-off and pick-up times, or in peak traffic, unless approved. Abnormal loads and mobile cranes will be planned separately.

How busy it will get

The contractor’s own forecast of construction vehicles by stage:

Stage When Trips a month Busiest day
Site set-up and clearance Q3 to Q4 2026 50 2
Below-ground structure Q4 2026 to Q1 2027 30 1
Main structure Q2 to Q4 2027 310 13
Services, fit-out and testing Q4 2027 to Q4 2028 120 to 130 5

The peak month is forecast as October 2027, at 320 trips. The plan says Bennett took possession of the site in September 2026 and expects to finish in the last quarter of 2028.

The rest of the scheme

Native Land, the developer, closed £132 million of finance for St Mary’s Wharf in October. It has also asked for an extra storey with eight more homes, which Historic England and the National Trust oppose. That application is separate and has not been decided.

What it means for you

  • If you walk along Millbrook past the site, expect to use the pavement on the other side of the road once the hoarding goes out.
  • Drivers on the A281 should expect lorries turning in and out of the pit lane during the day, and occasional lane closures for crane work. Those closures will need Surrey County Council approval first.
  • The council has not yet approved the plan. You can read it in full on the planning register under 23/D/00169/15.