Guildford's town centre flood scheme is in detailed design. A planning application is due in 2027 and works should finish in early 2032, if the money is found.
The flood defence scheme for Guildford town centre now has a timetable. A planning application is due in the third quarter of 2027, and the works are set to be finished in the first quarter of 2032.
The dates are in a report to Guildford Borough Council’s Executive, which meets on Thursday 3 December (Shaping Guildford’s Future report, PDF). The Environment Agency leads the scheme, working with the borough council and Surrey County Council.
The agency says its aims are to cut flood risk to the town centre, to improve the river environment, and to “build better connections between Guildford town centre and the River Wey” (Environment Agency scheme page).
The timetable
The Environment Agency sent its outline business case to its assurance board in June 2026. It was signed off in September, which unlocked the money for detailed design. The council’s report sets out the next steps:
| Stage | Target date |
|---|---|
| Outline business case approved | September 2026 |
| Detailed design starts | November 2026 |
| Planning application submitted | July to September 2027 |
| Planning permission | January to March 2028 |
| Preparation for construction starts | July to September 2029 |
| Works completed | January to March 2032 |
Not yet paid for
The scheme is not yet fully funded. The report says delivery depends on a final business case being approved and on “funding certainty”, with both government grant and match funding needed.
The council lists that as its main risk. Several town centre sites it owns cannot be developed until the flood risk is dealt with. The report names two:
- the Portsmouth Road car park
- Bedford Wharf
It also warns of a clash of timetables. The new Local Plan is due to be published for submission in March 2028, before the flood scheme’s funding is settled. Planners will have to decide how far they can count on those sites.
What the council is being asked to do
Officers ask the Executive to back the next stage of its town centre regeneration programme, Shaping Guildford’s Future. The work would cover:
- working with the Environment Agency through detailed design
- checking leases and tenancies to see when council land could come free
- testing developer and investor interest
- talking to Homes England about housing on council land
- talking to landowners and occupiers, including the Odeon and Royal Mail
It would use up to £125,000 already in the council’s regeneration budget. The council has also asked West Surrey Council, which takes over on 1 April 2027, for £250,000 to carry the work on through 2027/28 and 2028/29. That bid has not been approved.
The Executive is also asked to confirm the council’s commitment to redevelop Woodbridge Meadows. The report says more work is needed to find out what land there could come free, and when, given existing leases.
What it means for you
- Nothing changes on the ground yet. The scheme is in design. No construction is planned before the second half of 2029.
- You will get a say. A planning application is expected in summer or autumn 2027, and residents can comment on it then. The Environment Agency has held three public events on the scheme since 2024. It takes questions at Guildfordfloodscheme@environment-agency.gov.uk.
- The Local Plan is the other route. First consultations on the borough’s new Local Plan are due in April and May 2027. That is where the future of the riverside sites will be argued.
- Flood warnings still come from the Environment Agency. Until the defences are built, the town centre relies on the agency’s existing flood warning service for the River Wey.
The Executive meets at 7pm on 3 December (agenda).