Boxgrove Road starts closing overnight on 30 November for the £2m Boxgrove Roundabout rebuild. Ten raised crossings go in, and work pauses over Christmas.
Work to rebuild Boxgrove Roundabout in Guildford started on Monday 19 October. Surrey County Council expects the job to take about six months and cost £2 million.
Updated 22 November: the county’s 20 November project update says works on Boxgrove Road start on 30 November and involve overnight road closures, with a signed diversion. The kerbing round the new central island and the road foundation are finished, and tarmac and new signposts come next. The county says the next phase is being planned so it does not clash with the diversions from Dennis Roundabout, where it says National Highways’ works are overrunning. It is also working with SGN on a possible gas leak beside the site on Parkway (Surrey County Council).
The roundabout is where the A3100 London Road meets the A25 Parkway and A25 Boxgrove Road, on the edge of Burpham and Merrow. The county is adding raised zebra crossings with cycle lanes beside them on every entry and exit, so people on foot and on bikes have priority over traffic (Surrey County Council).
When the roads are affected
The county says its teams will work day and night:
- From 19 October: temporary traffic lights at night only, from 8pm to 6am
- During the day: no traffic lights and no road closures
- From late November: single arms of the roundabout close overnight, with signed diversions, starting with Boxgrove Road on 30 November
- Over Christmas: work stops for a few weeks
The county warns the work depends on the weather and the plan may change. It says residents will get letters and that warning signs will go up before each stage. Updates will go on the project page.
Surrey’s street works register lists the first stage of the job on London Road, Boxgrove Road and Parkway until 26 October (Surrey County Council roadworks).
What is being built
The detail is in the county’s traffic order notice, published on 10 July (notice, PDF). It lists ten raised parallel crossings, each one a zebra crossing for pedestrians with a marked cycle route alongside.
| Arm of the roundabout | Raised crossings |
|---|---|
| A25 Parkway (west) | 3, including one on the left-turn lane |
| A3100 London Road north (towards Burpham) | 3, including one on the left-turn lane |
| A25 Boxgrove Road (south-east) | 2 |
| A3100 London Road south (towards the town centre) | 2 |
Each crossing sits on a raised table across the full width of the road:
- the table is 75mm high and 7.5m long, with ramps at each end
- each crossing is 6.6m wide: a 3.2m zebra, a 3m cycle route and a 40cm gap between them
- a separate raised table goes across the exit from The Clockhouse retirement complex onto London Road
Shared paths for walking and cycling will run round the outside of the new roundabout (statement of reasons, PDF).
The county has published a scheme drawing showing the new kerb lines.
The trees and the money
The two large trees on the roundabout will stay where they are. The three smaller trees will be dug up and replanted round the outer edge, the county says.
The £2 million comes from Active Travel England, the government body that funds walking and cycling schemes. The county says the money can only be spent on active travel, and not on maintenance such as potholes.
The county says the design follows community engagement in 2023 and 2024, and that the feedback showed “strong support”. The formal objection period on the traffic order ran from 10 July to 7 August 2026. The county has not published how many objections it received.
What it means for you
- If you drive through after 8pm, expect temporary lights at the roundabout from tonight, and allow extra time.
- From late November, check the project page before late journeys. When an arm is shut overnight, you will be sent round a signed diversion.
- If you walk or cycle between Burpham, Merrow and the town centre, the finished roundabout gives you right of way on all four arms.
- If you live at The Clockhouse, your exit onto London Road gets its own raised table, and the county says access to homes will be kept “when it is safe to do so”.
Other closures this week, including Woking Road and the A3, are on our Guildford roadworks page.