Native Land has closed £132m of finance for 180 homes on Guildford's former Debenhams site. Main works start within weeks; sales open in spring 2027.

Building work on the former Debenhams site by the River Wey is about to restart. Native Land, the developer, says it has closed a £132 million financing deal for St Mary’s Wharf, its 180-home scheme in Guildford town centre (Native Land, 12 October).

The developer has also named its main contractor. Bennett Construction will take over the 1.7-acre site and start preparatory work immediately, with the main construction phase beginning “in the coming weeks” (Bennett Construction).

Native Land plans to launch sales in spring 2027. It expects the scheme to be finished before the end of 2028.

Where the money comes from

The £132 million is made up of two loans:

  • £100 million of senior debt from NatWest
  • £32 million of mezzanine finance from the National Housing Bank, a wholly owned subsidiary of Homes England, the Government’s housing agency

Mezzanine finance sits behind the main bank loan and carries more risk, which is why it usually costs a developer more. Native Land says the mix of Government-backed and private money will speed up housing delivery “across tenures”, meaning a mix of homes for sale and affordable homes.

This is the second funding round for the site. An earlier £18.5 million arrangement with Grosvenor, announced in March 2024, paid for the infrastructure phase (St Mary’s Wharf news).

Bar chart of development finance for St Mary's Wharf in Guildford: NatWest senior debt £100 million (2026), National Housing Bank mezzanine £32 million (2026), Grosvenor funding £18.5 million (2024).
Chart by The Guildford Post. Source: Native Land.
Share this chartFacebookWhatsAppX

What will be built

According to the two companies’ announcements, St Mary’s Wharf will have:

  • 180 apartments in two buildings, including affordable homes
  • shops, restaurants and cafés on the ground floors
  • about an acre of new public gardens
  • a continuous public riverside walk along the Wey
  • new walking and cycling links between the river and the High Street
  • an all-electric, fossil-fuel-free energy strategy and extensive cycle parking

The architect is Squire & Partners and the landscape architect is Gillespies. The whole development is about 200,000 sq ft, according to Bennett Construction.

Why it is 180 homes, not 185

When Guildford Borough Council approved the scheme in November 2022, Native Land described it as 185 private and affordable homes with 21,000 sq ft of shops and restaurants (Native Land, 23 November 2022). Every announcement now gives 180.

Native Land has been refining the approved design since demolition. It held a public drop-in at Guildford Baptist Church on 5 August to show changes, and said a planning application for them would be submitted later this year (St Mary’s Wharf consultation). Any change would need the council’s approval; until then, the 2022 permission stands.

What it means for you

  • If you live or work near Millbrook and Onslow Street: expect construction traffic to pick up once Bennett’s main phase starts. No road closures for the scheme have been announced yet. Our Guildford roadworks page will carry any that are.
  • If you want to buy: the sales launch is planned for spring 2027. You can register early interest through the St Mary’s Wharf website.
  • If you walk by the river: the riverside walk and gardens are part of the finished scheme, so they will not open before the buildings do.
  • If you want a say on the design changes: the amendment application, 26/P/01163, is on the council’s register and takes comments until 9 November. We explain it in St Mary’s Wharf extra storey: Historic England objects.

How the site got here

  • November 2022: planning permission granted for the Debenhams redevelopment
  • March 2024: £18.5 million funding arrangement with Grosvenor announced
  • Since 2024: demolition, basement and ground-floor works, flood protection and environmental improvements, according to Native Land
  • 5 August 2026: public drop-in on proposed design changes
  • 12 October 2026: £132 million financing closed and Bennett Construction appointed
  • Spring 2027: planned sales launch
  • Before the end of 2028: expected completion

In May the council described the site as being in a pause between phases, which we covered in our round-up of Guildford’s big planning schemes. Today’s announcements are the first to give a completion date.

Correction, 28 October 2026: this article originally told readers to watch for an amendment application. That application, to add a storey and eight homes, had in fact been lodged on 28 August as 26/P/01163. We have corrected the advice above.