The Environment Agency has withdrawn its flood objection to 1,800 homes at Gosden Hill, Burpham. The developer has lowered some buildings and set out a phasing plan.

The Environment Agency has withdrawn its objection to the 1,800-home Gosden Hill scheme on the edge of Burpham. It had objected in May over the flood modelling. In a letter dated 17 November, it said the model now “provides a suitable basis for assessing the flood risk outcomes” (Environment Agency letter, PDF).

That leaves National Highways as the main government agency still holding the plan back. Its last response, dated 1 September, asked Guildford Borough Council not to grant permission before 24 November. No newer National Highways response was on the planning register on 24 November.

The outline application, reference 25/P/01156, covers farmland between Burpham, Merrow Lane, the A3 and the railway. It is promoted by Martin Grant Land. The site is allocated for housing in Guildford’s Local Plan as Policy A25.

What the Environment Agency now says

The agency says the homes and other buildings would sit outside the area expected to flood in a 1 in 1,000 year event (a 0.1% chance each year). It withdrew its objection on one condition. Any later application setting out the layout must show that all built development stays outside that flood extent.

Surrey County Council, the lead flood authority for surface water, had already said it had no objection, subject to conditions, on 6 November (county council response, PDF).

What the developer has changed

The planning agent tor&co sent a revised set of drawings dated 5 November. They went on the register on 16 November. The covering letter says they follow comments from council officers and a meeting on 30 September (covering letter, PDF). The changes are:

  • lower buildings in the south-west corner, cut from four storeys to three. The letter says this answers concerns about long views and the setting of Clandon House and its registered park
  • more tree planting along the A3 edge on the northern boundary, asked for by the council
  • a safeguarded south-western road access removed, which the developer says Surrey County Council agreed at a meeting on 8 September
  • a planned “mobility hub” in the south removed. Officers felt it sat at the end of a route rather than where people would pass (summary of updated plans)
  • a new safeguarded walking and cycling access at an existing farm gate
  • a standalone plan showing the SANG, the public open space meant to draw walkers away from protected heathland

The letter calls these “principally a matter of fine-tuning”. It says they do not change the conclusions of the scheme’s environmental statement.

When the homes would be built

The revised phasing drawing gives the first firm timetable for the site (Indicative Phasing Strategy, PDF). It is marked indicative, and it depends on permission being granted.

Phase Dates What it includes
Phase 1 December 2027 to June 2029 Access road from Merrow Lane, drainage basins, a temporary foul pumping station, then about 150 homes
Phase 2 Not dated The new A3 junction and the London Road (A3100) access
Phase 3 July 2028 to June 2031 About 630 homes, the A3 junction and London Road access finished, the local centre and the primary school
Phase 4 July 2031 to December 2032 400 homes, the Gypsy and Traveller site, sports pitches and allotments
Phase 5 January 2033 to December 2035 About 620 homes
Phase 6 March 2034 to September 2035 The secondary school, “if required”

The commercial space and the Park and Ride are split half and half between phases 3 and 4. The drawing says the primary school would be finished at or around the time the 500th home is occupied, subject to the county as education authority.

Bar chart of homes planned in each Gosden Hill phase: about 150 in phase 1, December 2027 to June 2029; about 630 in phase 3, July 2028 to June 2031; 400 in phase 4, July 2031 to December 2032; about 620 in phase 5, January 2033 to December 2035.
Homes planned in each phase of the Gosden Hill scheme. Chart by The Guildford Post
Share this chartFacebookWhatsAppX

The drawing also says the secondary school may not be needed for some time. It cites projections of “significant reductions” in secondary-age children in the borough through to about 2043. It assumes delivery by 2034 only to line up with the end of the Local Plan period.

Work on the SANG would start in December 2027, subject to a felling licence from the Forestry Commission. It would have to be open before the first home is occupied.

The other responses this month

  • Thames Water said on 11 November that the foul water network “does not have sufficient capacity” for the scheme. It asked for a condition that no home is occupied until upgrades are done, or until a phasing plan is agreed with it. It says network modelling can take 9 to 12 months (Thames Water response, PDF).
  • Natural England said on 2 November it would be satisfied if the SANG costings cover setting it up and 80 years of management (Natural England response, PDF).
  • The Surrey Hills National Landscape adviser said the site is “well away” from the protected landscape and its proposed extensions (response, PDF).

The register still shows 190 objections and 2 letters of support among 196 public comments (public comments). Merrow Residents’ Association objected again in October, mainly over traffic. We covered that, and the National Highways questions, in our October report.

What it means for you

  • No decision has been made. The application is still listed as registered, with no committee date. The A3 junction design, queues on the new off-slip and the bus strategy were National Highways’ open questions in September.
  • If you live in Burpham or Merrow, the first homes would be reached from Merrow Lane. The A3 junction and the London Road access come later, under the phasing drawing.
  • You can still comment on the amended plans through the “Make a Comment” tab on the planning register, quoting 25/P/01156. Councils normally take comments into account until a decision is made.