National Highways' A3 junction and bus questions are the main block on 1,800 homes at Gosden Hill. The Environment Agency dropped its flood objection in November.
Overview
Updated 24 November: the Environment Agency withdrew its flood objection on 17 November, and the developer filed amended plans with a phasing timetable. National Highways’ 24 November date has passed with no newer response on the register.
Guildford Borough Council cannot approve the 1,800-home Gosden Hill scheme before 24 November without going against National Highways’ advice. The government roads agency says it still cannot judge the effect of the new A3 junction the plan depends on.
The outline application, reference 25/P/01156, covers the farmland between Burpham, Merrow Lane, the A3 and the London railway line. It was validated on 18 August 2025 and is still undecided 14 months later (planning register).
The register shows 190 objections and 2 letters of support among 196 public comments, from 724 neighbours consulted (public comments).
What the plan includes
The site is allocated for housing in Guildford’s adopted Local Plan as Policy A25. The application, submitted through the agent tor&co, is promoted by Martin Grant Land, according to the scheme’s own website (gosdenhill.co.uk). It seeks outline permission with only the site accesses fixed now. It includes:
- up to 1,800 homes, plus residential institution space (class C2, such as a care home)
- six Gypsy and Traveller pitches
- a local centre with shops and space for businesses
- land for a primary school and a secondary school
- a new junction onto the A3, and new accesses from London Road and Merrow Lane
- a Park and Ride
- allotments, play areas, sports pitches with a pavilion, and a SANG (a public open space meant to draw walkers away from protected heathland)
Active Travel England describes the secondary school site as 2.41 hectares, four forms of entry and 600 places (Active Travel England response).
Why there is no decision yet
National Highways runs the A3. Its latest formal response, dated 1 September, says it is still waiting for information from the developer’s transport consultants and “unable to complete our formal review” (National Highways response).
It recommends that the council does not grant permission until 24 November. The council could still refuse the application before then, or agree a longer extension. National Highways has sent four earlier responses, in October and December 2025 and in March and June 2026.
The outstanding questions it lists are:
- the A3 junction design. Some drawings have arrived and are under review. A road safety audit, a walking, cycling and horse riding assessment and further design drawings are still needed before a decision.
- queues on the new A3 off-slip. It has asked for extra traffic modelling of the slip road down to the new roundabout. Uneven use of the lanes could cause queues long enough to create safety risks on the slip road and the A3 itself.
- the bus strategy. National Highways says “a key concern remains” that the scheme’s targets for people travelling by bus, bike and on foot “cannot be met”. The developer sent an updated bus strategy to Surrey County Council on 30 June, which National Highways says it has not seen.
Where the other agencies stand
| Body | Latest position on the register |
|---|---|
| National Highways | Do not grant before 24 November (1 September 2026) |
| Environment Agency | Objection withdrawn, subject to a condition (17 November 2026) |
| Active Travel England | “Deferral”: not able to support the plan yet (3 August 2026) |
| Network Rail | Earlier concerns settled by a list of station improvements (7 August 2026) |
The Environment Agency objected on 26 May. It said the flood model was “not currently suitable” for a site-specific flood risk assessment (Environment Agency, May).
On 10 September it said the hydrology concerns had been dealt with. One issue remained: the flows put into the model did not match the report’s own table. It asked to be consulted again once that was fixed (Environment Agency, September). A second addendum to the flood modelling study went on the register on 28 September.
Active Travel England, the government’s walking and cycling body, has kept its position of “deferral”. It also questions the developer’s forecast of only 66 car arrivals at the secondary school in the morning peak, when about half of the school’s trips are expected to start outside the new estate.
Network Rail has dropped its earlier concerns. It agreed with the developer and South Western Railway a list of station improvements that could be paid for through a section 106 agreement (Network Rail response). All prices are plus VAT and linked to inflation:
- Clandon station: a waiting shelter for taxi and lift pick-ups on the Guildford-bound side, £16,500
- Clandon station: a waiting room in the unused station building on the London-bound side, £65,625
- London Road (Guildford) station: signs to the nearby bus stops, £3,000
- London Road (Guildford) station: a larger covered cycle store with 48 spaces, £104,971.20
By our addition, that comes to about £190,000.
What residents’ groups say
Merrow Residents’ Association wrote again on 6 October to reinforce its objection (letter). It says the developer has made no real attempt to answer its concerns about traffic.
The association wants a relief road built now, running south of the A3 from the site to the A247 at Garlick’s Arch. It says that would take some northbound traffic away from Burpham and Merrow. It notes that the Local Plan lists this road as an “opportunity” for the site, and that land has been set aside for it in the plans.
It also says the station upgrades “would do nothing whatsoever” to reduce traffic congestion. And it backs a call from Burpham Neighbourhood Forum for the council to ask the developer for one consolidated set of documents. More than 350 documents now sit on the register.
What it means for you
- The earliest realistic decision is late November, unless the council refuses the plan first. The register currently lists the case as a decision for officers, but no committee date has been set.
- You can still comment. The formal consultation period ended on 23 March, but councils normally take comments into account until a decision is made. Use the “Make a Comment” tab on the planning register, quoting 25/P/01156.
- If you drive the A3 or London Road, the junction design and the bus plan are the parts to watch. London Road is already being dug up at Boxgrove for the county’s £2 million roundabout rebuild, and our roadworks page carries the latest closures.