National Trust bridge repairs in Guildford: water is back over the new Tumbling Bay weir, but the footbridge stays shut a few weeks more. Timeline and detours.

The footbridge over the Tumbling Bay weir in the centre of Guildford is a few weeks from reopening. It has been closed since the weir collapsed in 2019.

Water is now running over the new weir at Millbrook. The National Trust, which looks after the River Wey Navigations, calls it “the latest milestone” on its project page.

The towpath over the bridge is not open yet. Tristan Brown, the Trust’s general manager for the River Wey Navigations, said in a statement on 14 October: “The engineering project to replace Millbrook Weir and footbridge is coming to an end.” He added that “the bridge will remain closed for a few more weeks while a small section over the sluice gate is built off-site.” The statement was published by the Guildford Dragon.

The Trust has not given a reopening date.

Updated 13 November: the Trust’s November update on its project page, headed “The project enters the final stage”, repeats that the bridge “will remain closed for a few more weeks” while the section over the sluice gate is built off-site. It still gives no reopening date.

What has been done

The weir and footbridge collapsed together in 2019, and a temporary weir was put in to hold the river level. The Trust appointed contractors Knights Brown to replace both, with the work running through the summer and autumn of 2026 (National Trust).

The Trust’s own timeline of the job:

  • May: the contractor’s compound went up in the Millbrook car park, off the A281
  • June: a crane arrived, and river levels were held about 2 inches lower than usual for the rest of the works
  • July: the gabion baskets and walls put in as a stopgap in 2020 were removed, and piling began
  • August: piling finished and work started on the new weir walls
  • September: the new pier walls were built and the concrete base of the tumbling bay was well underway
  • October: water returned over the new weir
Timeline of the Millbrook weir and footbridge rebuild in Guildford: collapse in 2019, contractor's compound in May 2026, crane in June, piling from July, piling complete in August, pier walls and concrete base in September, water back over the new weir in October, and the bridge due to reopen within weeks once a sluice section built off-site is fitted.
Graphic by The Guildford Post. Source: National Trust.
Share this chartFacebookWhatsAppX

The Trust says its engineers designed the new weir to reuse as much of the material in the temporary structure as possible. The work had to fit a “narrow 3-month window” of low water, which the Trust warned put some risk on the timetable.

Why the weir matters

The Trust believes there has been a weir on the site since the 12th century. Mill owners built it to hold back water and drive their wheels. Today it keeps the water level up along the river through the town.

It is a fixed crest weir: water tumbles over it from one level to the next, which is where the name comes from. It also holds three sluice gates that are raised or lowered by hand to adjust the level. The footbridge crosses the weir channel and links the towpath to the green island beyond.

What it means for you

  • Walking the towpath: the bridge is still closed. Until it reopens, the short detour stays in place, rejoining the towpath at Guildford Rowing Club or the Yvonne Arnaud Theatre.
  • Diversion maps: the Trust publishes five, including from Millmead Lock, from Millbrook weir and approaching Millmead from the south.
  • On the water: the navigation stays open. The Trust says there may be short safety closures when materials are lifted over the river by crane.
  • Parking: part of the Millbrook car park off the A281 has been the contractor’s compound since May.

We will update this page when the Trust confirms the reopening date. For other closures in town, see our Guildford roadworks and travel page, and for parking options, parking in Guildford.